A crane that lifts a 100 tonne module from a supply boat onto a platform is not solving the same problem as a tower crane on a building site, even though both hang a load on a wire. The platform crane’s base is bolted to a structure that does not move; the supply boat’s deck heaves under the load before it ever leaves the chocks, and by the time the hook takes the weight the crane can be seeing 140 or 160 tonnes on a wire rated for a static 100. That gap between the static weight and the dynamic hook load is the whole subject of offshore lifting, and it is why an offshore crane rated in still water carries a separate, lower rating once a sea state is named. This article is the hub for the offshore cranes and heavy-lifting cluster. It explains the equipment, the dynamic loading that derates it, the splash-zone physics that makes a subsea lift the most dangerous phase of all, the rigging that connects the hook to the load, and the planning and survey discipline that decides whether a lift goes ahead. The cluster’s worked calculation, the crane pedestal overturning moment calculator, sizes the moment the lift drives into the supporting structure, and the crane dynamic factor calculator builds the DAF that everything else rides on.
The logic of the topic is one question asked at every stage: what is the real load? Not the weight on the data plate, but the force the crane, the wire, the sling, the shackle, and the pedestal actually carry at the worst instant of the lift. Offshore, that force is the static weight multiplied by a chain of factors for vessel motion, hoisting acceleration, hydrodynamic effects in the water, and a margin for the consequence of a drop. Get the chain right and the lift is routine; get it wrong and the wire parts or the crane tips. The standards that govern this, DNV-ST-0378 for the crane, DNV-RP-N103 for the marine operation, API Spec 2C for the pedestal crane, and the IMCA lifting guidance for the procedure, all exist to pin down that chain of factors and the conditions under which it holds.
The lifting equipment: pedestal cranes against heavy-lift vessels
Offshore lifting splits into two families of equipment, and the split is about where the lift capacity comes from. A pedestal crane mounts a slewing crane on a fixed column, the pedestal, welded or bolted to a platform deck, a jack-up, or a vessel. The pedestal carries the entire overturning moment of the lift down into the structure, and that moment, not the hook capacity alone, often sets the limit. A heavy-lift vessel, by contrast, puts the lift capacity in the hull: a sheerleg (a fixed, non-slewing A-frame derrick on a barge) or a semi-submersible crane vessel (SSCV) with one or two revolving cranes uses the buoyancy and ballast of a large hull to resist the lifting moment, which is how a single hook reaches into the thousands of tonnes.
A platform pedestal crane is a workhorse rated in the tens to low hundreds of tonnes, used for routine deck lifts, supply-boat transfers, and equipment changes. Its rating is set by the crane structure, the wire and hook, and critically the strength of the pedestal and the deck beneath it, which is why the overturning moment is the governing calculation. The moment is the load times the radius times the dynamic factor, and it grows fast as the load swings out: a 50 tonne load at a 25 metre radius drives a static moment of 1,250 tonne-metres before any dynamic factor, and the crane pedestal overturning moment calculator sizes exactly that demand on the supporting steel.
Sheerlegs and crane vessels
A sheerleg is the simplest heavy-lift answer: a rigid A-frame or pair of inclined legs raked over the bow or stern of a barge, with the hook hanging from the apex. Because the legs do not slew, the load is positioned by moving the whole barge, which is slow but gives a very high fixed capacity for the steel involved. Sheerlegs of 3,000 to 5,000 tonnes are used for harbor and nearshore lifts, bridge sections, and jacket placement in sheltered water. The trade-off is the lack of reach and the dependence on barge position, so sheerlegs work best in calm, controlled waters rather than open-sea installation.
A semi-submersible crane vessel solves the open-water problem by combining a low-motion hull with one or two revolving cranes. The semi-submersible form floats on submerged pontoons connected to the deck by slender columns, so the waterplane area is small and the vessel’s heave, roll, and pitch response to waves is far gentler than a barge’s. That low motion is what lets an SSCV lift in an open-sea wave climate where a barge-mounted crane would be weather-bound. The largest such vessels lift in the range of 5,000 to over 14,000 tonnes per crane and run the two cranes in tandem for the heaviest modules. The heavy-lift and project cargo calculator frames the vessel-and-cargo side of these spreads, and the cluster’s wider context sits in subsea and offshore installation.
The crane rating is conditional, not a single number
A landside crane has one load chart: capacity against radius. An offshore crane has a family of charts, because the rating depends on the sea state. DNV-ST-0378 lets the safe working load be defined either for the still-water (in-harbor) condition or for a stated significant wave height, and offshore cranes carry both. The still-water chart is the headline number, the figure that gets quoted; the offshore chart, derated for a named significant wave height, is the one that governs an actual sea lift. The same crane might be rated 100 tonnes at 20 metres in harbor and 60 tonnes at 20 metres in a 2.0 metre significant wave height, because the dynamic factor that multiplies the working load rises with the sea state. Reading the wrong chart is a classic and dangerous error: a lift planned against the harbor figure can overload the crane in any real seaway.
The dynamic amplification factor and the hook load
The central number in offshore lifting is the dynamic amplification factor. The DAF is the ratio of the maximum dynamic load to the static load: a dimensionless multiplier, always at least 1.0, that turns the weight on the data plate into the force the crane and rigging actually carry at the worst instant. A DAF of 1.3 means the hook sees 130% of the static weight; a DAF of 2.0 in a heavy splash-zone lift means it sees twice the weight. Every downstream sizing, the wire, the sling, the shackle, the spreader bar, the pedestal, is done against the dynamic load, not the static one.
The DAF exists because nothing in an offshore lift is static. The crane base moves with the vessel, so the load is already accelerating before lift-off. The hoist itself accelerates the load when the wire takes up. The load swings as the crane slews and the vessel rolls. And once the load is in the water, hydrodynamic forces add and subtract from the wire tension as waves pass. DNV-ST-0378 builds the DAF for the crane, and DNV-RP-N103 gives the formulations for the marine-operation side, in particular for the wave-zone crossing. The crane dynamic factor calculator assembles a working DAF from a base factor, the hoisting speed, and the sea state, the form DNV uses for an in-air offshore lift.
| Symbol | Meaning | Unit |
|---|---|---|
| Base dynamic factor | ||
| Hoisting speed | m/s | |
| Sea state at lift | m |
Source: DNV-ST-0378; API Spec 2C
Calculate DNV-ST-0378 →Building the design load factor by factor
The hook load is not a single multiplier dropped on the weight; it is a stack of factors, each covering a different effect, and the design practice is to identify the weight first and then build the chain. The starting point is the gross weight, which is itself uncertain, so a weight-contingency factor is applied to cover the difference between the calculated and the as-built weight, larger early in a project and smaller once the object has been weighed. A center-of-gravity envelope factor covers the uncertainty in where the weight acts, because an offset CoG shifts the sling loads. The dynamic amplification factor then covers the motion and acceleration. A skew or tilt factor covers uneven sling loads when the rigging is not perfectly symmetric. The result is a design load that can be 1.5 to 2.5 times the bare weight, and the table below shows the shape of a typical in-air build-up.
| Factor in the chain | Typical range | What it covers |
|---|---|---|
| Gross object weight | 1.00 (the base) | Calculated or weighed dry weight of the lifted object |
| Weight-contingency factor | 1.03 to 1.10 | Difference between calculated and as-built weight; larger early, smaller after weighing |
| Center-of-gravity envelope | 1.05 to 1.10 | Uncertainty in the CoG position, which skews the sling loads |
| Dynamic amplification factor | 1.10 to 2.00+ | Vessel motion, hoisting acceleration, swing; rises with significant wave height |
| Skew / tilt factor | 1.05 to 1.25 | Uneven load sharing across slings when rigging is not symmetric |
| Consequence / safety factor | applied to MBL | Margin between working load and the wire or accessory breaking load |
The factors compound, so a 100 tonne object with a 1.05 contingency, a 1.08 CoG envelope, and a 1.30 DAF presents a design hook load of about 143 tonnes before the consequence factor that sets the wire’s required breaking strength. This is why an offshore lift uses far more rigging than the static weight suggests: the wire and the slings are sized against the compounded design load, then a further factor separates the working load from the minimum breaking load. The exact factors come from DNV-ST-0378, DNV-RP-N103, and the project’s lifting specification; the practice is consistent even where the numbers differ by project.
Where the DAF comes from physically
The DAF is not a fudge factor; it is the dynamic response of a mass on a spring driven by the vessel motion. The lift wire is a spring, the load is the mass, and the moving crane tip is the driver. When the driving frequency (the vessel’s heave period) approaches the natural frequency of the wire-and-load system, the response amplifies, and a poorly chosen lift configuration can put the natural period near a dominant wave period and resonate the hook load up. Long wire payouts soften the spring and lower the natural frequency; short stiff wires raise it. This is why a deep subsea lift on a long wire behaves differently from a deck lift on a short one, and why the lift analysis models the wire stiffness, the load mass, and the vessel motion together rather than picking a single DAF off a table.
Onshore against offshore: the moving base and the water
The difference between an onshore lift and an offshore lift is not a matter of degree. It is two physical conditions that an onshore crane never faces. The first is the moving base. An onshore crane stands on firm ground or outriggers on a prepared pad, and the only motion in the system is the load swing the operator controls. An offshore crane stands on a vessel that heaves, rolls, and pitches with the sea, so the crane tip describes its own path through space independent of the operator, and the load inherits that motion through the wire. The lift-off itself is a hazard onshore-lift planning does not have: as the hook takes the weight off a heaving deck, a downward deck motion can slam the full weight onto the hook in an instant, and an upward motion can re-lift the load after it has cleared, so the moment of lift-off is a controlled snatch, not a smooth take-up.
The second condition is the water. An onshore load stays in air from pick to set. A subsea lift lowers the load through the sea surface and down to the seabed, and the moment it touches the water the load picks up forces that have no onshore equivalent: buoyancy that reduces the effective weight, added mass that increases the apparent inertia, drag that resists motion, and, at the surface, slamming and the risk of a snap load. These are the forces DNV-RP-N103 was written to model, and they make the splash-zone crossing the governing case for the whole lift even though the object spends only seconds passing through it. The offshore support and marine operations hub covers the vessels that carry out these operations, and the subsea and offshore installation hub covers the installation campaigns they serve.
The weather window is the schedule
A third practical difference follows from the first two: offshore lifting runs on weather, not on dates. Every offshore lift has a set of limiting criteria, a maximum significant wave height, a maximum wind speed, sometimes a current and a swell-direction limit, and the lift proceeds only inside a forecast window where the criteria hold for the duration of the operation plus a margin. A heavy lift that takes eight hours needs a window longer than eight hours with a confidence margin, because a window that closes mid-lift can strand a partly installed module in a rising sea. The DAF and the weather window are linked: a lower wave-height limit means a lower DAF and a higher allowable load, so a project trades capacity against waiting time. An onshore lift simply waits out a windy day; an offshore lift can wait weeks for a season’s weather to give a long enough window, and the cost of that waiting is often larger than the lift itself.
The splash zone: slamming, snap loads, and the subsea lift
The splash zone is the band of water near the surface where a lowered object is partly in and partly out of the water and the wave action is strongest. It is the most dangerous phase of a subsea lift because the forces there are large, fast, and reversing. As an object enters the water, the rising face of a wave hits it with a slamming impact force that depends on the slam coefficient, the wetted area, and the square of the relative velocity between the water surface and the object. As the object submerges further, buoyancy builds and reduces the net weight on the wire, and added mass increases the inertia the wire must accelerate.
The hazard is the combination: while the object is in the splash zone, the wire tension swings between a high value at slam and a low value as buoyancy and an upward wave lift the object. If a wave lifts the object faster than the crane pays out the wire, the wire goes completely slack, and when the wave drops away the load drops back onto a slack wire and snatches it tight. That snatch is the snap load, and it can spike the hook tension to several times the static submerged weight in a fraction of a second. A snap load that exceeds the wire’s safe working load parts the wire and drops the object, which is the dominant failure mode of subsea lifting. DNV-RP-N103 treats the wave-zone crossing as the critical design case precisely for this reason.
Crossing the splash zone safely
The defenses against the splash-zone hazard are about controlling the relative velocity between the object and the water. A fast, decisive crossing through the surface, timed to a wave trough, minimizes the number of wave cycles the object spends in the danger band. A heave-compensated winch, active or passive, lets the wire pay out and haul in to follow the wave so the object’s vertical motion tracks the water and the relative velocity stays low, which keeps the wire in tension and prevents the slack-then-snatch sequence. Designing the object with holes and vent paths reduces the trapped-water slamming and the added mass. And limiting the lift to a low significant wave height keeps the wave-induced velocities below the threshold where snap loads occur. The lift analysis under DNV-RP-N103 computes the slamming force, the varying buoyancy, and the wire-tension envelope across the crossing, and the limiting sea state falls out of the requirement that the minimum tension stay positive (no slack) and the maximum tension stay below the wire’s rating.
Setting the object on the seabed
The lift does not end at the splash zone. Below the surface the object continues to feel drag and added mass, and on the way down the wire tension settles toward the submerged weight as the wave effects fade with depth. The landing on the seabed is its own controlled event: the object must be set down softly enough not to damage it or disturb the seabed, which means slowing the descent and managing the wire tension as the load transfers from the wire to the ground. For deep lifts the wire’s own weight becomes a large fraction of the hook load, and the lowering can run into the limit where the wire cannot support its own length plus the object, which is one reason very deep installations use fiber rope or staged lifting rather than a single steel-wire payout.
Rigging: slings, shackles, spreader bars, and the SWL
The rigging is everything between the crane hook and the lifted object, and it is sized against the design hook load, not the static weight. The basic accessories are wire-rope or synthetic round slings, shackles that connect slings to padeyes and to each other, and spreader bars or lifting frames that hold the sling angles within limits and keep compression out of the lifted structure. Each accessory carries a safe working load (SWL), also called the working load limit, which is the maximum load it may carry in service, and a minimum breaking load (MBL), the load at which it is expected to fail. The ratio between them is the design factor, and for offshore lifting accessories it is typically in the range of 3 to 5 on the MBL depending on the accessory and the standard.
Sling angle is the detail that catches people. A two-leg or four-leg sling shares the load between legs only when it hangs vertically; as the legs spread to an angle from vertical, the tension in each leg rises by the inverse cosine of the angle, so a wide sling angle can double the leg tension for the same load. A four-point lift with legs at 45 degrees from vertical puts about 1.41 times the per-leg vertical load into each sling, and at 60 degrees it is 2.0 times. This is why spreader bars exist: a spreader holds the slings vertical or near-vertical above the object so the leg tensions stay close to the shared static value, at the cost of the spreader’s own weight and the buckling check on the bar in compression. The shackle-to-metres converter handles the anchor-chain sense of the word shackle, distinct from the lifting shackle discussed here.
Marking, certification, and inspection
Rigging is not just sized; it is documented and inspected. Under the UK Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), every lifting accessory used at work, including shackles, slings, and eyebolts, must be marked with its safe working load and must be thoroughly examined at intervals (every six months for accessories) by a competent person, with a report kept. Offshore, the rigging loft keeps a register of every certified item with its identification, SWL, last examination date, and proof-test record, and an item without a current certificate does not go on the hook. The inspection looks for the failure signs specific to each accessory: broken wires and corrosion in wire slings, cuts and chemical damage in synthetic slings, distortion and wear at the crown and pin of shackles. Non-destructive testing (magnetic particle inspection on shackles, for example) supplements the visual examination on critical items.
Padeyes, trunnions, and the lift points on the object
The rigging connects to the object at its lift points, and those points are part of the lift design. A padeye is a plate with a hole welded to the structure that takes a shackle; a trunnion is a stub axle the sling cradles around. The lift points must be placed so the slings clear the structure, so the resultant of the leg tensions passes through the object’s center of gravity (or the object hangs at a controlled tilt), and so the local steel can carry the design sling load including the out-of-plane component when the sling does not pull exactly in the padeye’s plane. Padeye and trunnion design is a structural check in its own right, and on an engineered lift it carries the same design factors as the rest of the chain. The center-of-gravity position drives the sling-load distribution, which is why the CoG envelope factor sits in the load build-up: a CoG that is off where the rigging assumed puts more load into some slings than the symmetric calculation predicts.
Lift planning and the lift categories
Offshore lifting is governed by a planning discipline that scales the controls to the risk of the lift. The IMCA guidelines for lifting operations, the consolidated document carrying the references LR 006, SEL 019, D 060, and M 187, set out a category structure that operators across the offshore industry follow. The categories run from routine through non-routine to engineered, and the documentation, the competence required of the lift supervisor, and the level of approval all step up with the category. The point of the structure is to put engineering effort where the risk is, and not to bury a routine deck lift under the paperwork an engineered subsea lift needs.
| Lift category | Also called | What it covers | Controls required |
|---|---|---|---|
| Routine | Standard, simple | Repeated, well-understood lift within the crane’s normal envelope, pre-approved rigging | Generic risk assessment, competent operator and banksman, pre-use check |
| Non-routine | Complex | One-off lift, blind or tandem lift, lift near a limit, lift over live equipment | Specific lift plan, toolbox talk, named lift supervisor, defined limits |
| Engineered | Heavy, critical | Lift needing engineering analysis: DAF study, rigging design, CoG envelope, often subsea or float-over | Detailed lift study, calculated rigging loads, written procedure, MWS approval where insured |
A routine lift is the daily work of a platform crane: a basket of stores off a supply boat, a pump skid moved across the deck, a lift the crew has done many times within the crane’s chart and with rigging already certified for the job. It runs on a generic risk assessment, a competent operator, and a banksman to control the load. A non-routine lift is anything outside that comfort zone: a lift to or from a position the operator cannot see (a blind lift), a load too long or heavy for a single hook so two cranes share it (a tandem lift), or a lift over equipment that cannot be shut down. It needs a specific lift plan that names the rigging, the weights, the limits, and the people, and a toolbox talk before it starts. An engineered lift is a project in itself, with a lift analysis carrying the DAFs, a rigging design with every sling and shackle load calculated, a CoG envelope, and a written procedure, and it is the category that subsea lifts and float-overs fall into.
The roles around the lift
Every offshore lift has a defined set of roles, and the planning assigns them by name. The lift supervisor or person in charge plans and controls the operation and has the authority to stop it. The crane operator runs the crane and is responsible for not exceeding the chart. The banksman or signaller directs the operator when the load is out of the operator’s sight, using standard hand or radio signals. The rigger or slinger attaches and detaches the rigging and checks the accessories. On an engineered lift a lifting engineer owns the analysis and the rigging design. The competence of each role is documented (offshore crane operators in many regions hold a stage-3 certificate or an equivalent), and a lift does not start until the roles are filled by people qualified for the category of lift.
Dual-crane and tandem lifts
When a load is too heavy for one hook, or too long to hang stably from a single point, two cranes lift it together in a tandem (or dual-crane) lift. Tandem lifting is not simply adding the two cranes’ capacities. The load shares between the hooks according to the geometry, and any difference in the two cranes’ hoist speeds, any tilt of the load, or any vessel motion can shift load from one crane to the other, so a tandem lift can overload one crane while the other is well within its chart. The planning derates each crane (commonly to 75% to 80% of its chart) to leave headroom for the load shift, models the load sharing as the load tilts, and coordinates the two hoists so they move together. A tandem lift is always a non-routine or engineered lift; it is never routine.
On a semi-submersible crane vessel with two cranes, a tandem lift between the vessel’s own cranes is a standard heavy-lift method for the largest modules, with the two cranes’ load monitoring tied into one control so the split is managed actively. A tandem lift between two separate vessels is far harder, because the two hulls move independently and the relative motion between them feeds straight into the load share, so it is reserved for cases with no single-vessel answer and is planned with the vessels’ relative motion as a governing input. The offshore topside installation lift calculator frames the heavy-lift installation case these spreads carry out.
Float-over installation of topsides
When a topside is too heavy for any crane, even the largest SSCV, it is installed by float-over rather than lifted. A float-over carries the integrated topside on a vessel or barge, maneuvers it into a slot in the substructure (a jacket or a gravity-base structure) so the topside’s support legs sit directly over the substructure’s mating points, and then transfers the weight from the vessel to the substructure by ballasting the vessel down, often timing the operation to a falling tide so the sea helps lower the vessel. The load transfer is the critical moment: as weight comes off the vessel and onto the substructure, the vessel rises and its motion characteristics change, and the transfer must pass through the unstable middle of the exchange quickly and under control.
The hardware that makes a float-over work is the mating system. Leg-mating units (LMUs) sit on top of the substructure legs and receive the topside’s stabbing cones, guiding the topside into position and cushioning the vertical impact as weight transfers. Deck-support units (DSUs) on the vessel carry the topside during transport and release it cleanly during the transfer. The whole operation runs inside a tight window of vessel position, heading, and tide, with the relative motion between the vessel and the fixed substructure as the limiting criterion, and it is always an engineered operation with a marine warranty surveyor in attendance. A float-over trades the crane’s dynamic-lift problem for a ballast-and-motion problem, and for topsides of 10,000 tonnes and up it is often the only feasible method. The broader installation context sits in subsea and offshore installation, and the specialized-operations context in offshore, cruise and specialised operations.
The marine warranty surveyor
A heavy lift, a subsea installation, or a float-over is reviewed by an independent marine warranty surveyor before it goes ahead. The MWS is appointed by the insurer or the warranty holder, not by the contractor doing the work, and the surveyor’s job is to confirm, on behalf of the parties carrying the risk, that the operation meets an agreed standard of care. The MWS reviews the engineering: the lift analysis and its DAFs, the rigging design and the accessory certificates, the weather criteria and the forecasting, the vessel’s suitability and condition, and the written procedures. When satisfied, the MWS issues a Certificate of Approval for the operation, and the surveyor (or a representative) attends the operation to confirm that the limiting criteria, the named significant wave height, the wind limit, the load weights, are actually met before the go-ahead is given.
The MWS holds real authority because the project insurance is tied to the approval. If the operation proceeds without the surveyor’s sign-off, or outside the approved criteria, the insurance may not respond to a loss, so the contractor cannot simply overrule the surveyor and lift anyway. This is a contractual and insurance mechanism, separate from the statutory class and flag-state surveys that certify the vessel and the crane as equipment; the MWS approves the operation, not the hardware. The role concentrates the discipline of offshore lifting into one independent check: the same DAFs, rigging factors, and weather limits that the categories and standards describe are what the surveyor verifies before the lift starts.
How the cluster fits together
This hub carries the full topic of offshore cranes and heavy lifting because the cluster has a single deep calculation at its core. The crane pedestal overturning moment calculator is the cluster’s worked tool: it takes the load, the radius, and the dynamic factor and returns the moment the lift drives into the pedestal and the supporting structure, the figure that often sets a platform crane’s real limit. The crane dynamic factor calculator builds the DAF that feeds the moment, the wire sizing, and the rigging design, from a base factor, the hoisting speed, and the sea state in the DNV form. Together they cover the two numbers an offshore lift turns on: how big the dynamic load is, and how much moment it drives into the structure.
The lifting topic sits inside the wider offshore domain. The vessels that do the lifting, the construction-support vessels, the crane barges, and the supply boats that feed them, are covered in the offshore support and marine operations hub, including the AHTS bollard-pull capability that positions and holds the lifting spreads. The campaigns the lifts serve, laying pipe, installing subsea structures, and setting jackets and topsides, are covered in subsea and offshore installation. And the broader set of specialized offshore and passenger operations, of which heavy lifting is one branch, sits in offshore, cruise and specialised operations. The heavy-lift and project cargo calculator and the crane tipping moment calculator round out the lifting tool set with the vessel-and-cargo and the SWL-against-radius views of the same problem.
Limitations
This article describes the physics and the discipline of offshore lifting; it does not replace the governing standards, the project lifting specification, or the judgment of a qualified lifting engineer and marine warranty surveyor for a specific operation. The dynamic amplification factors and the load build-up shown here are illustrative of the structure of an offshore lift analysis, not values to lift by: the actual factors come from DNV-ST-0378, DNV-RP-N103, API Spec 2C, and the project’s own specification, and they depend on the crane, the wire, the object, the water depth, and the named sea state. A real lift is analyzed with the specific masses, geometries, and metocean data, and the limiting sea state is computed, not read off a generic table.
The lift categories (routine, non-routine, engineered) follow the IMCA guidance structure, but each operator’s lifting procedures define the exact boundaries and the controls for each category, and the competence requirements for the crane operator, the lift supervisor, and the rigger vary by region and by the regulatory regime in force. The splash-zone and snap-load treatment is the qualitative picture of what DNV-RP-N103 models quantitatively; the actual slamming forces, added mass, and wire-tension envelopes require the full hydrodynamic analysis with the object’s geometry and the wave kinematics. The rigging design factors, the SWL-to-MBL ratios, and the LOLER examination intervals are the common offshore practice, but the controlling figures are those on the accessory’s certificate and in the applicable standard. None of the linked calculators replaces an engineered lift study, a competent person’s examination of the rigging, or a marine warranty surveyor’s approval for a specific lift.
See also
- Subsea and offshore installation: the pipelay, subsea-structure, and jacket-and-topside installation campaigns that the lifts serve.
- Offshore support and marine operations: the construction-support vessels, crane barges, and supply boats behind the lifting spreads.
- Offshore, cruise and specialised operations: the wider offshore and specialized-operations domain this cluster sits within.
- Crane pedestal overturning moment calculator: the moment the lift drives into the pedestal and supporting structure.
- Crane dynamic factor calculator: the DNV-ST-0378 dynamic amplification factor from base factor, hoist speed, and sea state.
- Crane tipping moment calculator: the SWL-against-radius tipping check for a crane.
- Offshore topside installation lift calculator: the heavy-lift topside installation operation.
- Heavy-lift and project cargo calculator: the vessel-and-cargo side of a heavy-lift spread.
- AHTS bollard-pull calculator: the anchor-handling tug capability that positions the lifting spreads.
- Shackle-to-metres converter: the anchor-chain shackle length, distinct from the lifting shackle.