ShipCalculators.com

Extended Operational and Trade Vocabulary

LNG Operations and Custody Transfer glossary (page 2)

The cargo and custody-transfer vocabulary of LNG: aerating and gas freeing, the AGA-8 equation of state and energy metering for custody transfer, air drying and inerting, the ALARP risk principle, and the boil-off, rollover, and tank-gauging terms. Grounds each term in the custody-transfer calculation or the gas-handling procedure it belongs to.

355 defined terms.

Showing 105 on this page (page 2 of 2).

P

PR EoS
See Peng-Robinson EoS; alternative to KMR for density per GIIGNL.
Pre-Cooling
General term covering tank cool-down with LNG spray nozzles before bulk transfer.
Pressure Build-Up Coil
External vaporizer on Type C tanks creating tank pressure for discharge.
Primary Barrier
Innermost CCS layer in contact with LNG, e.g. 1.2 mm corrugated stainless on Mark III.
Primary Insulation Space (PIS/IBS)
Space between primary and secondary barriers, monitored by N2 pressure and HC content.
Process Safety Information (PSI)
Required under terminal PSM programs (US OSHA 29 CFR 1910.119).
Pt-100 RTD
Platinum resistance temperature detector, primary cryogenic temperature sensor; class-approved per GIIGNL.
Pump Tower
Stainless steel truss structure inside membrane and SPB tanks supporting cargo pumps and instruments.
Pump Tower Base Support (PTBS)
Reinforced support for the pump tower foot designed for cyclic sloshing loads.
Pump Trip
Automatic stop on low NPSH, motor overcurrent, or ESD activation.
Purging
Sequential N2 displacement of CH4 from inerted piping prior to opening for maintenance.

Q

Q-Flex
210,000 to 217,000 m3 LNG carriers, 14 in fleet built for Qatargas, propelled by twin slow-speed engines with onboard reliquefaction.
Q-Max
263,000 to 266,000 m3 LNG carriers, 14 in fleet for Qatargas, dual reliquefaction trains; world's largest LNGCs.
QCDC (Quick Connect/Disconnect Coupling)
ISO 21593 type powered coupling used in LNG bunkering.
Quad Fuel
Capability to burn HFO, MGO, BOG, and forced gas; common on TFDE installations.
Quayside power
shore power outlet on the apron.

R

Radar Gauge
Primary level gauge; FMCW microwave inside still pipe, Saab/Honeywell/Endress+Hauser supply.
Rated Loading Rate
Terminal-specified maximum cargo flow, typically 10,000 to 14,000 m3/h on conventional jetties.
Receiving Terminal
Onshore facility unloading, storing, and regasifying LNG for pipeline send-out.
Recondenser
Onshore vessel mixing send-out LNG with BOG to condense vapor before HP pumping.
Reference Temperature
Standard temperature for LNG volume reporting, typically minus 161.5 degrees C per GIIGNL.
Reliquefaction plant
BOG handling unit on LNG carriers.
Repeatability (CTS)
Required accuracy of radar gauges typically +/- 5 mm per GIIGNL Handbook.
RGS (Re-Gasification System)
Process train on FSRU or onshore terminal converting LNG to send-out gas.
Roll Period
Time for one complete oscillation; approximated by T = 2 pi k / sqrt(g GM).
Rollover
Spontaneous density inversion in LNG storage tanks causing rapid BOG release; mitigated by recirculation and stratification monitoring.
Rotterdam TTF
Title Transfer Facility, European natural gas price benchmark used in LNG indexation.
RV (Relief Valve)
Spring or pilot-operated valve on tank vapor dome set per CCS designer.

S

Saab TankRadar
Brand of Emerson Marine radar gauges widely used as CTMS primary; certified per IEC 60079.
Samsung Heavy Industries (SHI)
Korean shipbuilder, leading membrane LNGC yard.
SBT (Segregated Ballast Tanks)
LNGC double-hull ballast wings independent of cargo system.
Schlumberger Sampling System
Continuous probe sampling for LNG terminal GC.
Secondary Barrier
Liquid-tight barrier capable of containing cargo for 15 days at IGC design conditions in case of primary failure; full on Mark III/NO96, partial on Moss/SPB.
Send-Out Pump
Onshore HP pump delivering 60 to 100 barg LNG to vaporizers.
Settling Period
Time after loading before custody transfer measurements, allowing density and temperature stabilization, typically 30 min to 2 h.
Ship-Shore Compatibility Study
Pre-arrival check covering manifold geometry, mooring, ESD, and gangway per OCIMF/SIGTTO.
Ship-Shore Safety Checklist (SSSCL)
Joint document signed at berthing per SIGTTO LNG Shipping Suggested Competency Standards.
Shrinkage
Density reduction of LNG mix during regas/recondensing accounted for in custody transfer.
SIGTTO
Society of International Gas Tanker and Terminal Operators; principal industry safety body for LNG carriers and terminals.
SIGTTO Competency Standards
Suggested LNG officer training and assessment framework adopted by major operators.
SIGTTO ESD Arrangements and Linked Ship/Shore Systems
Reference standard for ESD-1/2 implementation at LNG terminals.
SIGTTO Liquefied Gas Handling Principles
Standard textbook for LNG/LPG cargo officers (4th edition, 2016).
SIGTTO LNG STS Transfer Guidelines
Authoritative guideline for LNG ship-to-ship operations.
Single Containment Tank
Onshore LNG tank with steel inner and earth-bermed or low outer wall; older design.
Skirt
Cylindrical support beneath Moss spherical tank attaching to the inner hull at the equator.
Sloshing
Dynamic liquid motion causing impact pressures on membrane; restricts partial fills 10 to 70 percent on many carriers.
Slow Steaming
Operating below design speed to save fuel and reduce emissions.
Small-Scale LNG
Vessels typically 1,000 to 30,000 m3 using IMO Type C tanks for distribution.
Smit Inert Gas
OEM of inert gas generators commonly fitted to LNGCs.
SNAM Method
Italian method for LNG density (Klosek-McKinley variant).
Soft Yoke Mooring (SYMS)
Permanent mooring system used for some FSRUs.
SPB (Self-Supporting Prismatic Type B)
IHI independent prismatic tank with internal bulkheads; used on Pacific Pintail, Polar Eagle, and Prelude FLNG.
Spray Header
Distribution line feeding cool-down nozzles in cargo tanks.
Spray Pump
Small deepwell pump in pump tower delivering LNG for cool-down spray and forcing vaporizer.
SSSCL
See Ship-Shore Safety Checklist.
Stabilization Period
GIIGNL-specified waiting time after pump stop before CTMS readings.
Steam Turbine Propulsion
Traditional LNGC propulsion using dual boilers (Mitsubishi, KHI) consuming HFO and BOG.
STM (Subsea Turret Mooring)
Permanent mooring for FLNG units (e.g., Prelude).
Stratification
Vertical density layering of the water column resisting mixing.
STS LNG Transfer
Cargo transfer between two LNG vessels using hoses or hard arms with dedicated fenders.
STS Plan
Master-approved STS Operations Plan per MARPOL Annex I/IMO Resolution adapted to LNG.
Sub-Cooler
BOG handling unit cooling forced LNG to absorb BOG before discharge or send-out, partial reliquefaction principle.
Subnet ESD
Local ESD loops on individual valves, integrated into vessel-wide ESD logic.
Surge Pressure
Hydraulic transient during fast valve closure; mitigated by slow ESD valve closing and surge tank in some terminals.

T

Tank Cover
Insulated stainless cover on Moss tank protrusion above deck.
Tank Dome
Top tank penetration housing instrumentation, vapor lines, and safety valves on prismatic tanks.
Tank Gauge Table
Capacity table issued by class society after laser survey, used in CTMS volume calculation.
Tank Pressure
Operating cargo tank pressure typically 1.06 to 1.25 barg.
Tank Test Pressure
1.25 times MAWP per IGC pneumatic test.
Temperature Sensor (Cargo)
Five Pt-100 sensors per tank (top, three liquid levels, bottom) per GIIGNL minimum.
Terminal Compatibility Matrix
Database matching ship size, manifold, and ESD with terminal acceptance window.
TFDE (Tri-Fuel Diesel Electric)
Wartsila 50DF or MAN 51/60DF engines burning HFO, MGO, and gas with electric propulsion.
TGE Marine
OEM of small-scale LNG carriers and Type C tank systems with onboard PBU.
Topside Manifold
Ship deck assembly hosting cargo presentation flanges, drip trays, and emergency shutdown valves.
TPS (Total Pressure System)
Type C tank vessel pressure control approach.
Trim and List Correction
Software adjustment in CTMS converting measured level to true volume with trim/list angles, drawing on calibrated tables.
Trim Tank
Aft ballast tank used to manage trim during loading and discharge.
Trunk Deck
Raised central walkway atop membrane LNG carriers housing liquid and vapor headers and pump tower trunks.
Type 2G Ship
IGC notation for LNG carriers per chapter 19 hazard categorization.

U

UFL (Upper Flammable Limit)
Maximum vapor concentration that will ignite.
UHP Vapor Line
High-pressure vapor return path from BOG compressor to engines or recondenser.
Ullage
Empty space above liquid cargo in a tank.
Unloading Operations Manual
Cargo officer reference detailing discharge sequences and vapor return procedures.

V

Vacuum Pressure
Negative tank gauge limit per IGC, typically minus 1 kPa, monitored to prevent membrane collapse on Moss/membrane.
Vapor Arm
Cryogenic loading arm returning vapor displaced during loading to shore BOG handling.
Vapor Crossover
Header on jetty enabling vapor return without dedicated arm.
Vapor Dome
Top tank dome through which vapor line and safety valves are installed.
Vapor Header
Common deck line connecting tank vapor domes to compressors and manifold.
Vapor Return Blower
Shore blower returning BOG from ship vapor manifold during loading.
Vapor Return Line (VRL)
Pipework from ship's vapor manifold to shore during loading or discharge.
Variable Frequency Drive (VFD)
Speed control for cargo and send-out pumps reducing electrical consumption.
VHP (Vapor Handling Plant)
Onshore equipment set including BOG compressor, recondenser, and HP pump.
Volume at Reference
Cargo volume corrected to minus 161.5 degrees C and 1.01325 bar per GIIGNL.
Volumetric Custody Transfer
Method computing energy from volume, density (KMR or PR EoS), and GHV (ISO 6976/GPA 2172).

W

Wartsila 50DF
Dual fuel medium speed engine for LNG carriers and dual fuel installations.
Water Curtain
Spray system protecting hull steel from cryogenic spills near manifold area on LNG carriers and jetties.
WinGD X-DF
Low-pressure dual-fuel two-stroke engine family.
WinGD X-DF2.0
Evolution of X-DF reducing methane slip via revised combustion timing.
Wobbe Index
GHV divided by square root of relative density; key gas quality parameter regulated by pipeline operators.
Working Pressure
Operating tank pressure typically 0.07 to 0.25 barg on membrane and Moss.

X

X DF
WinGD dual fuel two stroke engine family using low pressure Otto cycle.

Y

Y-Strainer
Inline cryogenic strainer protecting pumps and meters; common on bunker delivery lines.
Yarrow Boiler
Historic marine boiler type fitted on older steam turbine LNGCs.

Z

Zero Boil-Off (ZBO)
Operational state achieved on reliquefaction-equipped carriers (Q-Flex, Q-Max) where all BOG is reliquefied.
Zone 0/1/2 (IEC 60079)
Hazardous area classification used in IGC chapter 10 cargo zones for electrical equipment selection.