ShipCalculators.com

Extended Operational and Trade Vocabulary

Port Engineering, Dredging, Breakwaters, and Quays glossary

Vocabulary of port and coastal engineering: concrete armour units such as Accropode and A-Jack for rubble-mound breakwaters, ADCIRC hydrodynamic surge and tide modeling, cutter suction dredgers and anchor poles, and the breakwater, quay-wall and reclamation design terminology underlying harbour construction and protection works.

287 defined terms.

Showing 250 on this page (page 1 of 2).

A

A-Jack
Concrete armour unit with twelve legs used for shoreline and breakwater protection, manufactured under license by Armortec.
AAPA
American Association of Port Authorities, trade body representing seaports in the Americas.
Accropode
Single-layer concrete armour unit developed by Sogreah (now Artelia) of France in 1980 for rubble mound breakwater armouring.
Accropode II
Improved single-layer concrete armour unit developed by Artelia in 1999 as a successor to the original Accropode.
Active berth length
Length of quay actually available for berthing operations after deducting structural and operational setbacks.
ADCIRC
Two- and three-dimensional finite element hydrodynamic circulation model widely used in the United States for storm surge, tide, and coastal modeling.
Air gap
Vertical distance from the fuel surface to the top of the tank, used in ullage measurement.
Allowable axial load
Maximum vertical load that a pile or sheet pile section may carry within the design code's factor of safety.
Ambiorix
DEME self-propelled CSD of 19,200 kW total installed power, named after the Eburones chieftain.
Anchor pole
Auxiliary spud-like pole at the stern of a cutter suction dredger used to step the vessel forward between working positions.
Anchored sheet pile wall
Sheet pile quay restrained near the top by horizontal tie rods or strands connected to an anchor wall or pile group.
Approach channel
Navigable channel between sea and port basin.
Approach speed
Forward velocity of a CTV against the boat landing fenders, normally between two and four knots depending on swell and bow puffer design.
Arcelor sheet pile
Steel sheet pile sections, including the AZ, AU, and PU profile families produced by ArcelorMittal at its Belval mill in Luxembourg.
Armour layer
Outer protective layer of a rubble mound breakwater composed of rock or precast concrete units.
Armour rock
Large quarried stone placed as the outer protective layer of a rubble mound breakwater to resist wave attack.
As-built survey
Hydrographic survey carried out after dredging or construction to verify the work against the design.
ASPA
Antarctic Specially Protected Area, a Madrid Protocol designation requiring a permit for entry into ecologically or scientifically sensitive zones.
Athena
Jan De Nul CSD of 17,729 kW total installed, named after the Greek goddess of wisdom.

B

Backfill
Granular or rock material placed in a trench above a buried subsea cable to restore the seabed profile.
Backhoe Dredger
Hydraulic-excavator-mounted dredger.
Baggerwerken Decloedt
Belgian dredging firm, one of the two predecessors that merged in 1991 to form DEME Group.
Bartolomeu Dias
Jan De Nul TSHD of 17,500 m3 capacity, named after the Portuguese navigator.
Bathymetric survey
Seabed depth mapping campaign required for siting tidal arrays, wave farms, CO2 injection wells, and subsea hydrogen pipelines.
Beach nourishment
Coastal protection technique.
Bend Radius
Minimum curvature a wire rope or sling may follow without losing capacity.
Berm breakwater
Rubble mound breakwater with a wide seaward berm that allows the armour to reshape under wave action into a stable profile.
Berthing dolphin
Isolated marine structure designed to absorb the lateral berthing energy of vessels alongside a jetty.
BHD
Backhoe dredger acronym, in international tender documents.
Block-work quay
Gravity quay wall built from stacked precast concrete blocks bedded on a prepared rubble foundation.
Bollard
Mooring fitting on quay or dolphin.
Bollard pull
Tug pulling force in tonnes.
Booster station
Inline pumping unit installed on a dredger discharge pipeline to extend pumping distance when transporting slurry from cutter or hopper to placement site.
Boskalis
Dutch dredging and salvage major, parent of SMIT Salvage since 2010.
Bottom door
Hopper hull opening, hydraulically actuated, used for dumping sediment at sea.
Boulder protection
Heavy rock placed locally on the bed to deflect anchors or prevent scour around marine structures.
Bow thruster bay
Pocket recessed into a quay or jetty deck arrangement that accommodates bow thruster wash and may include scour protection.
Brabo
Trailing suction hopper dredger operated by Jan De Nul Group.
Brabo II
Successor trailing suction hopper dredger in the Jan De Nul fleet bearing the Brabo name lineage.
Breakwater
Coastal structure providing wave shelter.
Breasting dolphin
Isolated structure absorbing berthing impact.
Breasting line
Mooring line led roughly perpendicular to the berth, resisting off-berth motion of the vessel.
Bucket ladder dredger
Chain of buckets on inclined ladder, the oldest mechanical dredger type, still operating in tin mining off Indonesia.

C

Caisson breakwater
Vertical breakwater formed of monolithic or cellular reinforced concrete caissons set on a rubble foundation.
Caisson quay
Gravity quay wall constructed from floated-in reinforced concrete caissons ballasted and founded on a prepared bed.
Capital dredging
initial dredging to deepen or widen a channel or berth.
Cashman Dredging
United States dredging contractor based in Quincy near Boston, Massachusetts, active on coastal navigation and remediation projects.
Cathodic Protection
Sacrificial or impressed current system protecting subsea steel from corrosion.
CCCC
China Communications Construction Company, parent of the country's major dredging units including CHEC and the Shanghai, Tianjin, and Guangzhou dredging companies.
CEDA
Central Dredging Association, the European branch of WODA, headquartered in Delft.
Cellular caisson
Reinforced concrete caisson with internal cells that are flooded or filled with sand to provide stability against sliding and overturning.
Cellular cofferdam
Circular or diaphragm sheet pile structure filled with granular material, used as quay walls or temporary works in deep water.
Channel centerline
Reference line along which the design depth and width of a navigation channel are measured.
Channel cross-section
Geometric shape of a dredged navigation channel, typically trapezoidal in dredged sand and approximating triangular in narrow rock cuts.
Channel marker
IALA buoy or beacon.
Charles Darwin
Jan De Nul TSHD of 30,500 m3 hopper, one of the largest trailers in the world.
CHEC
China Harbour Engineering Company, the international engineering and dredging arm of CCCC.
Closure dam
Temporary or permanent earth or rock dam used to close off a tidal opening as part of reclamation or coastal works.
Combiwall
Composite sheet pile quay wall combining heavy king piles with intermediate light sheet piles to span between them.
Compaction grouting
Injection of low-mobility grout into loose granular soils to densify them prior to quay or breakwater construction.
Composite breakwater
Breakwater with a rubble mound base supporting a vertical concrete superstructure, common in deep water.
Concrete armour unit
Precast concrete element placed singly or in two layers as the armour of a rubble mound breakwater.
Container quay
Continuous quay wall designed for ship-to-shore container cranes and heavy stacking surcharges from the marshalling yard.
Conveyor
continuous belt for moving dry bulk between vessel, shore, and storage.
Core-loc
Single-layer concrete armour unit developed by the United States Army Corps of Engineers in 1996 as a successor to Dolos.
Cottrell Contracting
Virginia-based United States marine contractor active in dredging on the East Coast and Chesapeake region.
Crest level
Top elevation of a breakwater or revetment, determined by overtopping limits and design water level.
Cristobal Colon
Jan De Nul TSHD of 46,000 m3 hopper, tied with Leiv Eiriksson as the world's largest trailing suction hopper dredger.
Cross-shore transport
Movement of beach and nearshore sediments perpendicular to the shoreline driven by waves and water level changes.
Crown wall
Concrete superstructure cast on top of a rubble mound breakwater to limit wave overtopping and provide a service road.
CSD
Cutter Suction Dredger, removes hard material through a rotating cutter head.
Cutter head
Rotating toothed cutting tool at the lower end of a CSD ladder that excavates compact soils and rock.
Cutter ladder
arm carrying the cutter head on a CSD.

D

D'Artagnan
DEME CSD of 28,200 kW total installed power, named after the musketeer.
Daewoo E&C Marine
Marine and dredging arm of Daewoo Engineering and Construction of South Korea.
Deadman anchor
Buried plate or concrete block anchor that resists the tie-rod force of an anchored sheet pile quay.
Deep water quay
Quay wall designed for vessels with drafts greater than about 14 meters, typical of modern container, bulk, and tanker terminals.
Delft3D
Open-source modeling suite for hydrodynamics, morphology, and water quality.
DEME
Belgian marine contractor with subsidiaries including DEME Offshore active in foundation and turbine installation.
Design vessel
Reference vessel selected as the basis for sizing channels, basins, fenders, mooring fittings, and quay structures.
Design wave
Statistically derived extreme wave height used in structural design of offshore wind foundations.
Detached breakwater
Offshore breakwater for coastal protection.
DHI
Danish Hydraulic Institute, developer of the MIKE 21 and MIKE 3 modeling suites.
Diaphragm wall
Cast-in-place reinforced concrete wall built using bentonite-slurry trench techniques, sometimes used for quay walls in soft soils.
Discharge pipeline
Floating, sinker, or shore pipeline that carries pumped slurry from a CSD or hopper dredger to the placement area.
Disposal area
Designated water or land site for placement of dredged material, licensed under the London Convention for marine disposal.
Dolos
Concrete armour unit shaped like an H with twisted flukes, invented by Eric Merrifield in East London, South Africa in 1963.
Dolphin
Isolated marine structure.
Donjon Cape May
Donjon Marine yard in Cape May, New Jersey, that supports East Coast dredging and marine construction operations.
Donjon Marine
US east coast salvage contractor with OPA 90 OSRO standing.
Drag arm
Suction pipe assembly of a TSHD, including gimbal, intermediate sections, and drag head.
Drag head
Drag head of a trailing suction hopper dredger.
Drag head visor
Movable shield on a drag head that adjusts to soil conditions and helps direct material into the suction inlet.
Dragline
Crawler crane with drag bucket, historically used for marsh dredging.
Dredge cycle
Complete sequence of loading, sailing, discharging, and returning that characterizes TSHD productivity.
Dredge pump
Centrifugal pump, mounted inboard or outboard on a dredger, that conveys soil-water slurry through the suction and discharge piping.
Dredging International
Former name for DEME's dredging division.
Dredging tolerance
Permitted vertical deviation, including paid overdepth, between the design dredge level and the as-dredged bed.
Dustpan dredger
USACE Mississippi River dredger with wide horizontal suction mouth, exemplified by Hurley and Jadwin.

E

EADA
Eastern Dredging Association, the Asia-Pacific branch of WODA.
Earth pressure
Soil resistance against cutter, key driver of cutter motor sizing on CSDs.
Ebb shoal
Sand body deposited by tidal currents on the seaward side of a tidal inlet, often requiring maintenance dredging.
Echo sounder
Acoustic depth sensor.
EGD
Egyptian General Dredging, the state-owned dredging company affiliated with the Suez Canal Authority.
Embedment depth
Depth to which a sheet pile or king pile is driven below the dredge level to develop passive resistance.
Energy absorption
Capacity of a fender system to absorb the kinetic energy of a berthing vessel without exceeding allowable reaction forces.
Engineered armour unit
Precast concrete unit such as Tetrapod, Dolos, Accropode, Core-loc, or Xbloc used in place of natural rock on the armour layer of breakwaters.
Equilibrium beach profile
Idealized cross-shore beach profile that develops under prolonged average wave conditions.

F

Fairway
Navigable channel.
Fall-Pipe Vessel
Rock-dumping vessel installing protection over subsea infrastructure.
Fender pile
Pile installed in front of a quay or dolphin face that supports a fender system to absorb berthing energy.
Fender System
Timber, rubber or steel structures protecting bridge piers or lock walls from vessel impact.
Filter layer
Graded granular or geotextile layer placed between fine subgrade and coarse armour to prevent loss of fines.
Fixed bed model
Physical hydraulic model with non-erodible bed used to study hydrodynamics around port and coastal structures.
Flexible dolphin
Single tubular pile or pile cluster designed to deflect elastically under berthing impact.
Floating breakwater
Pontoon based wave attenuator.
Floating dock
U-shaped or L-shaped floating dry dock.
Free length
Length of a tie rod or anchor strand between the wall and the anchor block, treated as elastic in the design.
FUNWAVE
Open-source fully nonlinear Boussinesq wave model developed at the University of Delaware.

G

Geobag
Large geotextile bag filled with sand or grout, used for scour protection, breakwater cores, and temporary works.
Geosynthetic clay liner
Factory-manufactured composite of bentonite between geotextiles used to seal disposal cells and reclamation containment.
Geotextile filter
Permeable synthetic fabric placed beneath armour or scour protection to prevent loss of underlying fines while allowing drainage.
Gimbal
Pivot supporting jack-up leg-to-hull connection or crane base.
Gland water
Clean water supplied to dredge pump shaft seals to prevent abrasive slurry from damaging the gland.
Goliath
DEME giant backhoe dredger with 40 t bucket and 40 m reach.
Goliath II
Backhoe dredger operated within the DEME fleet, successor to the original Goliath.
Grab Dredger
Crane-grab-based dredger.
Grab hopper dredger
Self-propelled hopper dredger fitted with a grab crane that loads dredged material into the onboard hopper.
Granular column
Vertical column of compacted gravel installed in soft soils to improve bearing capacity and reduce settlement beneath quays.
Gravity quay
Quay wall whose stability against earth and water pressures relies on its own dead weight, typically built from caissons or blocks.
Gravity-base structure
Marine structure that resists loads by its own weight on the seabed, including caissons and concrete blocks.
Great Lakes Dredge & Dock
Largest United States dredging contractor, founded 1890 in Chicago and now headquartered in Houston, Texas.
Guangzhou Dredging Company
Dredging subsidiary within the CCCC group based in Guangzhou, China.
Guide Wall
A wall extending upstream or downstream of a lock entrance to align approaching tows.

H

Harbor basin
Sheltered water area within a port where vessels manoeuvre and berth.
Heavy-lift quay
Quay wall designed for very high deck and crane loads, typical of project cargo and offshore fabrication terminals.
Helios
Jan De Nul CSD of 23,200 kW installed, the largest CSD afloat alongside Spartacus.
Hellas
Trailing suction hopper dredger in the Jan De Nul fleet.
Hellespont
Trailing suction hopper dredger in the Jan De Nul fleet.
Hopper
funnel-shaped container receiving bulk from grabs and feeding conveyors or trucks.
Hopper bin
Compartment within the hopper of a hopper dredger that contains the dredged spoil.
Hopper coaming
Top edge of hopper, set above the loading line to retain overflow.
Hopper draft
Vessel draft of a hopper dredger, which varies as the hopper fills and discharges.
Hopper overflow
Controlled spill of excess slurry from the hopper of a TSHD during loading once the desired sand fraction is retained.
Hopper well
Open compartment in the deck of a TSHD that provides access to the hopper for loading and inspection.
Hyundai E&C Marine
Marine engineering and dredging division of Hyundai Engineering and Construction of South Korea.

I

IADC
International Association of Drilling Contractors; daily drilling report standard.
IAPH
International Association of Ports and Harbors.
Iconic armour unit
Specially designed precast unit, such as Dolos, used as a recognizable signature element on major breakwaters.
In-fill reclamation
Reclamation in which dredged sand is placed within a perimeter bund to create new land.
Inlet stabilization
Construction of jetties or training walls at a tidal inlet to fix its position and improve navigation.
Israel Dredging Co
Dredging company active in Israeli and Mediterranean ports.

J

J F J De Nul
Self-propelled cutter suction dredger operated by Jan De Nul Group.
Jacket
Outer protective casing on a tank container.
Jan De Nul Group
Belgian marine contractor operating WTIV Voltaire, floating heavy-lift vessel Les Alizes, and cable lay vessels Isaac Newton, Connector, and Willem de Vlamingh.
Jet ring nozzles
Ring of high-pressure water jets around a drag head or cutter that fluidize cohesive soil to aid intake.
Jet Trencher
Tracked or skidded subsea vehicle that fluidizes seabed sediments to embed cables and small pipelines.
Jet water
High-pressure water injected through nozzles on a drag head or cutter to mobilize sediment for pumping.
Jetty
Marine structure projecting from shore for berthing.
Joint Sealant
NSF-listed sealant used at junctions of food contact surfaces to provide cleanable continuity.

K

Kedge Anchor
Smaller secondary anchor carried for warping the ship off a grounding or to hold the stern in tide.
King pile
Heavy tubular or H-section pile that forms the primary load-carrying element of a combiwall quay between intermediate sheet piles.

L

Ladder
pilot ladder, accommodation ladder, or fixed quay ladder for personnel.
Landside apron
Paved area immediately behind a quay wall used for crane rails, container handling, or cargo storage.
Leeward apron
Rubble apron placed on the harbor side of a vertical or composite breakwater to protect the foundation from overtopping flows.
Leiv Eiriksson
Jan De Nul TSHD of 46,000 m3 hopper, sister to Cristobal Colon.
Levee
Earth or rock embankment built to contain water or dredged spoil within reclamation areas.
Lock Chamber
Enclosed basin of a lock between gates.
Long-period wave
Wave with period in the range of about 30 seconds to several minutes that can excite harbor resonance.
Lower discharge tube
Vertical pipe through the hull of a hopper dredger used for bottom or pump-ashore discharge of cargo.

M

Magnor
Backhoe dredger in the Boskalis fleet.
Maintenance dredging
periodic dredging maintaining design depths.
Manson Construction
Seattle-based US dredging contractor, second largest in US after GLDD.
MIKE 21
Two-dimensional hydrodynamic, wave, and sediment transport modeling suite developed by DHI.
MIKE 3
Three-dimensional hydrodynamic and ecological modeling suite developed by DHI.
Mole
Massive coastal structure projecting into the sea.
Mooring analysis
Static and dynamic mooring analysis per OCIMF and PIANC.
Mooring dolphin
Isolated structure for mooring lines.
Multibeam echo sounder
Hull or pole mounted sonar that ensonifies a swath of seabed in a single ping to produce high-resolution bathymetry.

N

Nautical bottom
depth at which density makes navigation impossible.
Navigation channel
Dredged or natural waterway providing safe passage for vessels between open water and a port or terminal.
Nominal armour size
Equivalent cube side length used to characterize armour rock or concrete units in stability formulas.

O

Open caisson
Caisson open at top and bottom, sunk through soft soils by excavation from within, used for deep foundations.
Open piled jetty
Marine berthing structure consisting of a piled trestle and deck rather than a continuous wall, used in deep water and soft soils.
Outfall
Discharge structure releasing wastewater to the sea.
Overdepth allowance
Additional dredged depth beyond the design level, paid to the contractor as a contractual tolerance.
Overflow plume
Sediment plume generated by hopper overflow during TSHD loading, an environmental concern in sensitive areas.
Overwidth allowance
Additional dredged width beyond the design channel width, paid to the contractor as a contractual tolerance.

P

Passing Distance
BMP5 recommendation to maintain at least 8 nautical miles from Somali coast in transit; greater off Yemen.
Pearl River
South China river system, with the Xi Jiang the principal navigable branch.
Penta-Ocean Construction
Tokyo-based marine contractor with TSHD and reclamation expertise across Asia and the Middle East.
Permeability layer
Coarse rock or geotextile layer that maintains drainage between armour and core of a breakwater.
PIANC
World Association for Waterborne Transport Infrastructure.
PIANC WG30
PIANC Working Group 30 report on approach channels, providing harmonized international design guidance.
Pile cap
Reinforced concrete element that ties together the heads of a pile group and transfers superstructure loads to the piles.
Piled embankment
Earth embankment supported on piles to limit settlement over soft soils behind quay walls.
Plain suction dredger
Stationary suction dredger without a cutter head, used in loose granular soils where the suction alone is enough to mobilize the bed.
Pneumatic Fender
Air-filled rubber fender, typically Yokohama-style, deployed between assisted vessel and quay.
Postnik Yakovlev
Backhoe dredger in the Van Oord fleet, named after the Russian master builder of Saint Basil's Cathedral.
Primary armour
Outer protective rock or concrete unit layer of a rubble mound breakwater, sized to resist the design wave.

Q

Quay wall
Vertical retaining structure forming berth face, designed under BS 6349.
Quayside crane rail
Steel rail embedded in the quay deck on which ship-to-shore container cranes travel.

R

Rainbowing
Discharge of slurry as a high-velocity jet from TSHD bow, used to build reclamation profile and as marketing icon.
Reclamation
Creating new land from the sea.
Reefer plug bank
Group of refrigerated container power outlets installed on the landside apron of a container quay.
Return Period
Average interval between events of a specified magnitude.
Revetment
A bank protection structure of articulated concrete mats or stone.
Ring anchor
Anchor or tie system that distributes anchor loads around a circular sheet pile cell or similar structure.
ROMS
Regional Ocean Modeling System, a free-surface, terrain-following ocean circulation model widely used for coastal studies.
Roundhead
Outer end of a breakwater, typically armoured with larger units due to higher local wave forces.
Royal Boskalis Westminster
Parent company of Boskalis Salvage and Boskalis Heavy Lift.
Rubble mound breakwater
Breakwater using armour stone and underlayers.
Run-up
Maximum vertical elevation reached by an individual wave above still water level on a sloping structure.

S

Salient
Cuspate accumulation of sand that builds in the lee of a detached breakwater without connecting to it.
Samson
Backhoe dredger in the Van Oord fleet.
Samsung E&C dredging
Dredging and marine reclamation activities of Samsung Engineering and Construction of South Korea.
Sand source
Borrow area from which sand is dredged for reclamation or beach nourishment.
Scour Protection
Rock or mattress placed at the base of offshore foundations to prevent seabed erosion that would expose cables.
Scow
Flat-bottomed barge used to transport dredged material from the dredger to a placement or disposal site, often with split or bottom doors.
Secondary armour
Filter layer of medium-sized rock placed beneath the primary armour of a rubble mound breakwater.
Sediment plume
Plume from dredging activities.
Segmented breakwater
Series of detached breakwater units separated by gaps, used to balance shoreline protection with longshore sediment transport.
Settlement
payment in discharge of the claim.
Shanghai Dredging Company
Major dredging company based in Shanghai within the CCCC group, active in Yangtze estuary and coastal projects.
Sheet pile interlock
Mechanical joint along the edge of a sheet pile section that engages adjacent sections to form a continuous wall.
Sheet pile quay
Quay wall formed by interlocking driven steel sheet piles, often anchored back to a deadman or rock anchor.
Ship-bank interaction
Hydrodynamic forces and yawing moments experienced by a vessel transiting close to a channel bank.
Side slope ratio
Ratio of horizontal to vertical run of a dredged channel or trench side slope, typically expressed as 1V:nH.
Significant wave height
Average of the highest one third of waves in a given period, the standard parameter governing CTV transfer limits.
Single Point Mooring
Generic term covering CALM, SALM, and turret moorings allowing weathervaning of moored tankers and FPSOs.
Skirt pile
Pile driven through a sleeve on a jacket or template to fix it to the seabed.
Sloping top caisson
Vertical breakwater caisson with an inclined upper face designed to deflect wave run-up and reduce overtopping.
Sounding
Measured depth.
Spartacus
DEME CSD of 44,180 kW total installed power, the world's most powerful CSD, delivered 2021 and LNG dual-fuel.
Split hopper
Hopper dredger or barge whose hull splits longitudinally to release the cargo by gravity.
Spud
A vertical steel beam dropped through a barge well into the riverbed to hold position.
Spud carrier
Movable trolley that carries the working spud of a CSD and allows the dredger to step forward without losing position.
Spud pole
Spud used as the working anchor and pivot point of a cutter suction dredger.
Squat
Loss of underkeel clearance due to speed in shallow water.
Submerged breakwater
Breakwater whose crest lies below the still water level, used to dissipate wave energy without obstructing views or navigation.
Submersible pump dredger
Suction dredger using a submerged pump mounted at the lower end of the suction or ladder to improve suction performance.
Suction inlet
Mouth of dredge pump suction pipe.
Suction pipe
Dragarm assembly on TSHD or fixed pipe on CSD.
Suez Canal Authority
Egyptian authority operating compulsory pilotage through the Suez Canal.
Swan
Boskalis semi-submersible heavy-transport vessel of the legacy Dockwise fleet.
SWASH
Simulating Waves till Shore, a non-hydrostatic wave-flow model developed at Delft University of Technology for nearshore and harbor applications.
Swing winches
Pair of winches that pull a CSD laterally around its working spud to cut an arc across the dredge face.

T

Telemac-2D
Two-dimensional shallow-water finite element hydrodynamic model in the open TELEMAC-MASCARET suite, originally developed by EDF.
Tetrapod
Four-legged concrete armour unit developed by Pierre Danel and Paul Anglès d'Auriac at Sogreah in France in 1950.
Tetrapod handling
Specialized lifting and placing of Tetrapod armour units using purpose-built clamps and templates.